Calling the Play

Morris Coordinates Bostic Construction

14 MIN READ
Mel Morris, President, Bostic Construction Inc. Bob RivesOn the Fast Track

Mel Morris, President, Bostic Construction Inc. Bob RivesOn the Fast Track

The Game Plan For Bostic Construction Inc., building a three-story, 24-unit apartment building in about 105 days is typical. To keep to its schedule, the company has agreements with its subcontractors that guarantee the subcontractors continuous work with the company if they agree to Bostic Construction?s schedule. Work is scheduled for every day: This timeline highlights some key days.

  • Day 1: Set corners
  • 5-6: Pour foundation
  • 13-14: Backfill/prep slab
  • 16: Pour slab
  • 18: Frame first floor walls
  • 23: Frame second floor walls
  • 26: Frame third floor walls
  • 27-30: Roof
  • 31-33: Shingles
  • 34-38: Rough HVAC and siding
  • 36-43: Rough cable, phone, and electric
  • 36-42: Brick veneer
  • 45-51: Insulation
  • 48-50: Sidewalks
  • 56 Drywall finish and hang
  • 65-67: railings
  • 71-72: first paint
  • 77-79: Install cabinets, interior trim, doors
  • 81: HVAC, plumbing, and electric final
  • 87-90: Final inspection, second painting
  • 95-100: Install carpeting
  • 101-103: Punch list
  • 103-105: Final clean
  • 105: Owner walkthrough