High Hopes

Cutting Time and Cost in High-Rise Development

6 MIN READ
Design build coupled with tunnelform construction allowed Ocean Villas, in Long Beach, Calif., to achieve construction costs that were 20 percent below similar projects in the area. The project will encompass a total of 576 units and 63,000 square feet.

Design build coupled with tunnelform construction allowed Ocean Villas, in Long Beach, Calif., to achieve construction costs that were 20 percent below similar projects in the area. The project will encompass a total of 576 units and 63,000 square feet.

Efficiency Goals The efficiency of the overall building layout must be considered during the design process. An overall goal of at least 85 percent building efficiency (net usable area to gross building area, not including parking) must be achieved.

Similarly, the ratio of exterior skin area to floor area must be no more than 50 percent. If these ratios are not achieved, it is unlikely the building’s overall costs will be in line.

Reducing construction time and cost is the key challenge in the design and construction of high-rise residential buildings. Without a relentless drive to lower costs and coordinate the design in a manner consistent with construction sequencing practices, the project will not meet the owner’s cost projections.

A thorough understanding of how to control construction time and cost can bring a project budget in line and make a project feasible.

–Brit L. Perkins, AIA, is a principal of EDI Architecture Inc. in Houston.

About the Author

No recommended contents to display.